Abu Dhabi, UAE
Abu Dhabi International Airport serves over 20 million passengers annually. And that number is growing every year.
To increase the capacity of the airport, and to propel it towards an ambitious future, the Abu Dhabi government commissioned a new $2.94bn terminal. The terminal construction features ground-breaking architectural design and will act as the centrepiece for the airport, covering an area of 630,000 m2 and servicing up to 20 million passengers per year.
For the TAV, CCC and Arabtec joint venture (TCAJV), bringing the iconic architectural vision to life required numerous shoring, propping and formwork solutions to accommodate for the sophisticated design and geometry of key parts of the structure.
Using the unique Megashor system, RMD Kwikform has supplied temporary support to the arch roof trusses up to 45 m high for the airport terminal construction within Abu Dhabi International Airport. RMD Kwikform succeeded in providing a working solution despite some challenging conditions including horizontal loads in excess of 100 kN, overturning and wind load, which had to be catered for by smart design and engineered connections.
Our engineers have used specialist 3D modelling techniques to design complex formwork and shoring solutions to support the delivery of the new Abu Dhabi International Midfield Airport terminal.
One of the most difficult design challenges was the formation of the main terminal building with its huge curved roof structure. This required the careful installation of some of the world’s largest steel archways and girders to create the impressive visual impact of this vital part of the airport construction project. Curving in both the horizontal and vertical axes, the construction of the terminal building relies on millimetre accuracy to install each specially fabricated segment which forms the arches and a central girder.
As part of the terminal construction planning process, RMD Kwikform engineers worked with steel roof sub-contractor China State Construction Engg Corporation (CSCEC) to design bespoke components and solutions using 3D modelling for the phased erection of the arches. This process included the design of a modular Megashor support system for the erection of the steel arches. This was coupled with additional shoring solutions for the steel buttresses and transfer slab that formed the foundations for the arches.
With a need to support the arches in both the vertical and horizontal planes, a critical component of the solution was the design of a special ball joint with an additional jacking frame system. To ensure the frame was able to cope with the critical loading forces and changeable climatic conditions, including high wind and heat, the engineering teams used the latest modelling technology before components were then fabricated and tested.
Commenting on the support solution, RMD Kwikform UAE General Manager Chris Jardine said: “Loading and stresses on the formwork and shoring were different for every single node point; we had to take a 3D model to form a solution that could operate safely and securely. As the contractor wanted to be able to use the frames multiple times, our solution had to be flexible enough to cope with the adjustments required at different parts of the erection phasing.”
In addition to designing the jacking frames, RMD Kwikform designed and supplied the support towers which varied in height from 15 to 45 metres.
Using its unique Megashor propping system, RMD Kwikform engineers had to vary the footprint of the towers to increase or reduce stiffness. This helped to optimise sharing of the load and to cope with thermal movements (due to temperature variance from day to night) of wind forces and dead loads. The support system had to cope with vertical loads of up to 500 kN and horizontal loads of up to 75 kN.
In addition, the Megashor system needed to be reused for subsequent steel arches, so the design had to be versatile and easy to reconfigure into a new tower design.
The steel buttresses and transfer slabs used to form the foundations for these steel arches were supported by RMD Kwikform’s high load Rapidshor modular steel shoring system. Each steel buttress weighed up to 40 tonnes and the concrete transfer slabs were up to 2.5 metres thick.
Finally, with each of the 16 steel buttresses and concrete slabs mounted two floors up, the RMD Kwikform team had to design a back-propping solution for the two levels below the raft. This was achieved using its lightweight aluminium Alshor Plus shoring system.
Commenting on the engineering challenges faced in the project, RMD Kwikform UAE Engineering Manager Anvar Sadat said: “To achieve the architect’s stunning vision for this structure, we’ve incorporated a lot of sophisticated engineering and design. Not only did the engineers have to account for extreme loading but loading in many different planes and variations due to the effects of both thermal changes and wind.”
TACJV also employed RMD Kwikform to design and supply equipment for several other structures for the Midfield Terminal construction project.
Construction of terminal building, and tunnel and bridge support
The project faced challenging conditions, including horizontal loads above 100 kN, overturning and wind load. The terminal construction included curved vertical and horizontal axes, requiring millimetre accuracy during design and installation. Thermal movements had to be accounted for due to significant temperature changes between day and night.
Heavy-duty propping, shoring, complex wall formwork
Complex slab solutions
This included back propping of the complex concrete structure of the airport slab. The slab itself had to be supported at key points to ensure the construction and halving joints, which created concrete cantilever structures, were formed correctly. Here our engineers designed a solution using Megashor to prop the concrete sections up to the raft levels on the transition areas before concrete pour strips completed the structure. Using the Megashor system also allowed other specialist trades greater access to the work area, as the system used fewer legs and beams, so it was easier to work around.
For the VIP area, Alshor Plus was used to support primary beams. These had a depth of up to 3.2 metres and a propping height of up to 13.5 metres. The Alshor Plus system reduced the number of loose components used and, being an aluminium system, it decreased the manpower needed due to its light weight but heavy loading capability. This allowed for the completion of this area in less than five months.
From internal bridges to ramps
The vast scale of the terminal building called for numerous additional projects, requiring engineering support. One such project was an internal long-span bridge. RMD Kwikform engineers designed modular Rapidshor steel shoring to support not only the concrete weight of the bridge but also its steel buttress and precast central beams. As part of the design process for this bridge the engineers had to consider other site users, achieving load transference to meet special restrictions for mobile equipment platform users and for those completing finishing works on the levels below.
Another unusual request saw engineers design a 20-metre temporary ramp with a five per cent slope, allowing a 40-tonne tower crane to be moved between two levels. By using Megashor and steel Superslim Soldiers, the solution proved to be far more convenient than constructing a concrete ramp; the speed of erection and dismantling assisted the overall access and programme management of the site.
Additional tunnel support
In addition to the main terminal building, RMD Kwikform equipment has also been used to provide solutions for a number of ancillary buildings and structures for contractor L&T. These include shoring and formwork for the construction of a traffic tunnel plus a three-carriageway road tunnel.
Talking about the scale of the construction, Project Director Adrian Brown from L&T, added: “The new Abu Dhabi International Midfield Airport Terminal building is a massive project, with several different construction phases. The engineering design and support that RMD Kwikform has supplied was vital in helping us to achieve some of the more complex engineering structures needed within the airport.”